Siding Project Update June 15, 2018

Almost two months in to the siding project here at Timber Creek the community is bustling with all the work that is getting done. We currently have nine buildings that are in one phase or the other of the siding project and the 10th building is about to get started next week. The project is ongoing with all the different parts and pieces that is necessary – everything from checking the existing siding to removal of siding that is identified as being removed, to adding the Water Resistant Barriers followed by all new window and door trim, corner boards, mud sills, weather barriers etc. Following that the painters come in to apply paint to all the running trim on the building, painting the existing wood windows to match the new style vinyl clad windows, painting the doors and then caulking of where the siding joins any trim.

All exterior gable end vents will be replaced with a new PVC vent, all dryer vents will be replaced, the electrician is going over all exterior electrical outlets to make sure we are in compliance with code and also removing exterior face mounted lights so that the siding can be installed and then the lights will be put back.

There are many moving pieces to this puzzle and it is an ongoing dialogue between management, architect, construction management and of course between the on-site superintendent and the contractors working on site. All in the project is progressing well and mostly according to schedule. Some adjustments are being made to meet schedules and to keep everything going as planned. It is definitely a very active work site Monday through Friday. Every effort is made to make sure the property is neat and clean for the weekends and to not leave anything in the way of unit access etc. We certainly appreciate items that have been brought to our attention by attentive homeowners.

Building 7 – units 35 through 38 is the building where most has occurred in the shortest time. It is one of the smaller buildings with four units and very little issues of any sort. The contractor is currently waiting for vent covers and some other material but continues the siding process where possible. It is exciting to see the transformation because that is truly what it is – a transformation from the old look to the new look.

We try to stay ahead in the project and communicate to owners in buildings that are being worked on or that are slated to have work started to keep them informed. So far so good.

Here are some photos showing the progress. As always, if you have any questions, do not hesitate to contact us.


May 10, 2018

Three full weeks in to the siding project and things are moving along. Currently six buildings are being worked on – building 1 (unit 1-6), building 4 (unit 17-24 and building 7 (unit 35-38) have had any siding removed that was slated for removal. The weather resistant barrier applied and installation of window, door and corner trim and the mud sill is ongoing on those buildings. Soon the painters will be on site to paint all trim and caulk so that the siding installation can start. On building 5 (unit 25-30), building 9 (unit 45-50) and building 17 (unit 95-98) crews are working on siding removal and applying the weather resistant barrier. The first couple of window replacements has also been done.

The large material deliveries (siding, trim etc.) have slowed down at the moment but there are daily deliveries of other materials (flashing, fasteners, drip cap etc.). You can definitely tell that there is a big project going on at Timber Creek. We are still fine tuning some things and getting the bugs worked out. There are weekly project meetings with Naylor & Breen (construction management), Goldstone Architecture and Timber Creek management.

Just a few photos below showing some of the work. I know everyone is anxiously waiting for photos showing the siding and it will come. In the meantime things are moving along and let’s hope that the weather will cooperate so the crews get full work days in and move the project forward.


THE PROJECT HAS STARTED!

Three full weeks in to the siding project and things are moving along. Currently six buildings are being worked on – building 1 (unit 1-6), building 4 (unit 17-24 and building 7 (unit 35-38) have had any siding removed that was slated for removal. The weather resistant barrier applied and installation of window, door and corner trim and the mud sill is ongoing on those buildings. Soon the painters will be on site to paint all trim and caulk so that the siding installation can start. On building 5 (unit 25-30), building 9 (unit 45-50) and building 17 (unit 95-98) crews are working on siding removal and applying the weather resistant barrier. The first couple of window replacements has also been done.

The large material deliveries (siding, trim etc.) have slowed down at the moment but there are daily deliveries of other materials (flashing, fasteners, drip cap etc.). You can definitely tell that there is a big project going on at Timber Creek. We are still fine tuning some things and getting the bugs worked out. There are weekly project meetings with Naylor & Breen (construction management), Goldstone Architecture and Timber Creek management.

Just a few photos below showing some of the work. I know everyone is anxiously waiting for photos showing the siding and it will come. In the meantime things are moving along and let’s hope that the weather will cooperate so the crews get full work days in and move the project forward.

On April 16, 2018 the siding project got started on site. Several of the crews were here and begun taking siding off the buildings. It was not warm outside, in fact, we had received fresh snow over the weekend, but that did not stop the crews who have anxiously been waiting to get going. They were ready to start and they sure did. It has been great to see what they have accomplished so far.

Our construction management company, Naylor & Breen set up their office trailer and have been receiving lots and lots of materials. There has been tractor trailer after tractor trailer arriving with siding, trim, house wrap, nails, caulk – you name it. Material deliveries will continue for quite some time so don’t be alarmed if you see an 18 wheeler pulling in to Timber Creek. And let’s hope they swing wide and miss the ditch at the entrance...

On April 20, 2018 we had the official “kick off” for the project and had the first of many onsite project meetings. These meetings will be ongoing to discuss the project, solve any issues, answer questions and do site visits. Since it was the official kick off we took the opportunity to snap a few pictures that you can see below.

TimberCreek siding project

The official “kick” off featured Dennis Wilson (board member), Jeff Goldstone (Architect - Goldstone Architecture), John (JTG Construction, Tanner Romano (VP & Project Manager – Naylor & Breen), Jason Wisell (Super Intendant – Naylor & Breen), and Minna Case (Property Manager).

Siding Removal and Work in progress

Phone: 802-464-0259 

Southern Vermont Deerfield Valley

P.O. Box 670 • Route 100 West Dover, VT 05356

Copyright 2011 © Timber Creek.  All Rights Reserved.
Go to top